[UPDATES] Vancouver Data Center Boost 15 October 2020

18 Aug 2020

 

Time Estimated

Action

Time Completed

5PM PST / 9PM AST


5PM PST / 9PM AST


5PM PST / 9PM AST

DC upgrade started.

 

Old BGP Broadcast stops. 

 

New BGP Broadcast starts. 

5:04PM

5:04PM

5:04PM

5:30PM PST / 7PM AST

Switch configured

5:30PM

6PM PST / 9PM AST

Switch programmed 6PM

6:30PM PST / 11PM AST

Testing new configuration & switches

6:15PM

7PM PST / 1AM AST

All servers live.

7:20PM